Update Activities

uuu_P6Start uuu_P6Finish uuu_P6Planned Start uuu_P6PlannedFinish uuu_P6ActualStart uuu_P6ActualFinish uuu_P6RemainingEarlyStart uuu_P6RemainingEarlyFinish Behavior after import
For Not Started Activity: Valid date provided No Change No Change No Change No Value No Value No Change No Change

Activity will be updated with uuu_P6Start update provided

uuu_P6Finish will be calculated based on Start and duration

All other dates - Planned Start, Planned Finish, Remaining Early Start and Remaining Early Finish will be updated same as Start and Finish

Activity status will be "Not Started"

No Change Valid date provided No Change  No Change No Value No Value No Change  No Change

Activity will be updated with uuu_P6Finish and duration will be recalculated

All other dates - Planned Start, Planned Finish, Remaining Early Start and Remaining Early Finish will be updated same as Start and Finish

Activity status will be "Not Started"

No Change  No Change  No Change  No Change  Valid Value entered No Value No Change  No Change 

Activity will be updated with uuu_P6Start same as uuu_P6ActualStart

Planned Start and Planned Finish will not be changed

Remaining Early start will be same as uuu_P6ActualStart and Remaining Early Finish will be same as uuu_P6Finish

Activity status will be "In progress"

No Change No Change No Change  No Change No Change  Valid date entered No Change No Change

Activity will be updated with uuu_P6Finish same as uuu_P6ActualFinish

Planned Start and Planned Finish will not be changed

Remaining Early start and Finish will not show any dates (empty) as the activity is being completed

Activity status will be "Complete"

Activity percent will be 100% (one hundred percent)

Note:

When you change any of the above dates, the system updates the dates accordingly. For activities that are marked as "Not Started," the values for the Start, Finish, Planned Start, Planned Finish, Remaining Early Start, and Remaining Early Finish will be the same.