Update Existing Activity (Not Started) to Start Milestone

uuu_P6Start uuu_P6Finish uuu_P6Duration Activity Status Activity Type uuu_P6ActualStart uuu_P6ActualFinish uuu_P6PercentComplete Behavior
Valid value provided  or not provided. Valid value provided  or not provided. Valid value provided  or not provided. Valid value provided  or not provided. Activity type is provided as  'Start Milestone' Not applicable Not applicable Not applicable

Activity will be created as milestone with Activity Type selected as "Start Milestone"

Activity Status will be "Not Started"

uuu_P6Start and uuu_P6Finish will be the same as project schedule start date

uuu_P6Duration will be 0 (zero)