Entering Modified Committed Line Items
If enabled and applicable, you can populate the Detail Form tab and additional tabs of a Change Order BP record with modified committed line items with their corresponding cost codes, quantities, and amounts.
Prerequisites
- You have the required permissions to create Change Order BP records.
- Populate the Main Form of the Change Order BP record as outlined in Creating a BP Record.
Online Mode
To populate a Change Order BP record with modified committed line items:
- Touch the Standard tab.
- To add a new line item, touch the Plus (+) icon and then select Modify Committed Line Item.
- From the Commit line item picker, select a line item.
- Depending on the type of cost associated with a line item, Unit Cost or Variable Unit Cost may display for the line item.
- For costed lines that were copied from the SOV, the following information displays in the cost breakdown of a Committed Line Item:
-
Cost Code: For SOV-referenced line items, displays the cost code from the Commit Line Item Picker (step 3).
For new costed line items, select a cost code from the CBS Picker.
- Code Name: Displays the name of the selected cost code
- Short Description: Displays the description from the Summary Line Item field by default. Enter or modify the description as needed.
-
Current Quantity: Displays the quantity purchased from the selected commit record.
For new costed lines, displays a blank.
-
Current Unit Cost: Displays the Item Unit Cost value from the selected commit record.
For the new costed lines, enter the unit cost of the line item. By default, displays blank.
-
Current Scheduled Value: For existing costed lines, displays the scheduled value from the SOV.
For the new costed lines, displays zero.
- Change Quantity: Enter the modified quantity for existing and new costed lines.
- Change Amount: Displays the value from the Current Unit Cost calculation.
- New Scheduled Value: Displays the calculated value from a combination of the Current Scheduled Value and the Change Amount fields.
-
Cost Code: For SOV-referenced line items, displays the cost code from the Commit Line Item Picker (step 3).
- To add multiple line items, repeat the entire above sequence.
- Touch the Cost Breakdown tab of a Standard line item, and perform any of the following actions:
- To save the current line item, touch Save.
- To continue adding line items, touch Save and Add New.
- To delete a costed line, swipe on a costed line and then touch Delete.
- To remove a new costed line item, touch Delete. Note, for committed costed line items from the SOV, the Delete option is not displayed.
- To copy a costed line, swipe on a costed line and then touch Copy. Note, the Current Scheduled Value is not copied.
- Finalize the line items and costed line items as needed.
- To complete the BP record, touch Send (for workflow BP records) or Submit (for non-workflow BP records).
- To save the record to the server and retain the record in an editable state, touch Save.
- To complete the submission of the record, touch Submit.
- To modify the record, touch Edit.
Result
- After the Change Order BP record is routed to the terminal step, the costed lines in the SOV are updated with modified values for Quantity and New Scheduled Value.
- For new lines, the variable unit rates provided in the cost breakdowns are rolled up to the SOV along with the Quantity and the Amount.