Adding a Template for Baseline Curve for Cash Flow by Summary CBS or CBS
To add a template for Baseline curve for cash flow by Summary CBS or CBS:
Cash Flow Properties Template Setup For a Baseline Curve by Summary CBS
When you select the Summary CBS option in the Detail Level drop-down list (General pane) and in the Curves pane you add Baseline curve (from the Curves drop-down list), proceed to set up the following parameters:
| Property | Description |
|---|---|
| Cost |
Note: You can choose the cost column when creating a curve in a project/shell but not in templates.Select your cost source as one of the following options:
|
| Schedule |
Define the range of dates to use for plotting the cash flow data. These are the dates you specify to start the curve and end the curve. Note: If you choose to take dates from the schedule sheet elements, the Master schedule sheet is used for the project/shell.Select one of the following options:
|
| Project Type | If you set Schedule to Use dates from Activity Sheet, select the project as either Baseline or Current. |
| From Date | If you set Schedule to Use dates from Activity Sheet, select the start date to use for plotting the cash flow curve. |
| To Date | If you set Schedule to Use dates from Activity Sheet, select the end date to use for plotting the cash flow curve. |
| Distribution |
Distribution profiles are used to distribute data automatically in the cash flow worksheet. Select a distribution profile to use as the default distribution profile for the curve. Select any of the following options:
|
| Variance |
For CBS, typically, the Variance is set to Inflow for a Baseline type curve. This value is used to calculate variances against the Outflow type curves. Your choices are:
|
Cash Flow Properties Template Setup For a Baseline Curve by CBS
When you select the CBS option in the Detail Level drop-down list (General pane) and in the Curves pane you add Baseline curve (from the Curves drop-down list), proceed to set up the following parameters:
| Property | Description |
|---|---|
| Bring Baseline Data From Distribution |
Specify the source of your baseline data. Select any of the following options:
|
| Data Type |
This field displays if you chose to Bring Baseline Data From a P6 Summary Sheet. Select any of the following values:
|
| Sheet Name | If you set Bring Baseline Data From Distribution to Activity Sheet, select an activity sheet. |
| Schedule & Distribution | If you set Bring Baseline Data From Distribution to Activity Sheet, select a column for the Schedule & Distribution method. |
| Cost |
Note: You can choose the cost column when creating a curve in a project/shell but not in templates.Select your cost source as one of the following options:
|
| Schedule |
Define the range of dates to use for plotting the cash flow data. These are the dates you specify to start the curve and end the curve. Note: If you choose to take dates from the schedule sheet elements, the Master schedule sheet is used for the project/shell.Select one of the following options:
|
| Project Type | If you set Schedule to Use Dates from Activity Sheet, select the project as either Baseline or Current. |
| From Date | If you set Schedule to Use Dates from Activity Sheet, select the start date to use for plotting the cash flow curve. |
| To Date | If you set Schedule as Use dates from Schedule Sheet or Use Dates from Activity Sheet, then select the end date to use for plotting the cash flow curve. |
| Distribution |
Distribution profiles are used to distribute data automatically in the cash flow worksheet. This option lets you select a distribution profile to use as the default distribution profile for the curve. Select any of the following options:
The Auto option is selected by default, if you selected the Schedule option as Use Dates from Activity. Additionally, if you also selected the Periods for Cost Distribution option as Honor working days, Auto displays as a read-only field, and you can no longer select a default distribution profile. |
| Periods for Cost Distribution |
This field displays only if you have selected the Schedule option as Use Dates from Activity Sheet, and Distribution as Auto. Select any of the following options to specify how to distribute the costs based on the activity schedule:
|
| Variance |
For CBS, typically, the Variance is set to Inflow for a Baseline type curve. This value is used to calculate variances against the Outflow type curves. Your choices are:
|