15 Maintaining the Schedule Manager
The Schedule Manager feature was deprecated starting with version 23.5. However, if you have access to it, you can continue to use it to:
- Update activities and submit changes to Linked Schedule Sheets.
- Link existing Schedule Sheets to project/shell Schedule Sheets.
- Configure data mapping to allow direct importing of external sources such as Microsoft Project or Primavera schedules.
Note:
Many tasks that you perform as an administrator are also available at the user level. This section describes only the tasks that are available at the administrator level. For tasks that apply to both levels, see the Unifier Managers User Guide for detailed instructions.
Beginning with version 26.6, you can use the Automated Schedule Migration Tool to migrate schedule data from Schedule Manager to manual Activity Sheets. As an administrator, configure the Field Mapping profile at the company level. Project users start the migration at the project level.