Project/Shell and Business Process Updates

To update a Business Process (BP) in the Project/Shell:

  1. Go to the shell tab, and switch to Admin mode.
  2. In the left Navigator, select Setup, and then select Business Process Updates.

Business Process Updates Log in Project/Shell

The Business Process Updates log in Project/Shell allows you to set up updates from a template to a record, at the Project/Shell level. The log consists of the following:

Menu

  • File
  • Edit
  • View
  • Help

Toolbar

  • New
  • Cancel Request
  • Open
  • Find
  • View Details

    Note:

    These options can be accessed through the Business Process Updates log menu options.

Columns

  • Name
  • Source Business Process
  • Source Business Process Record
  • Submit Date
  • Schedule date
  • Start Date
  • Completion Date
  • Status
  • Requested By

The functions of the elements in the Business Process Updates log are explained in the following section.