Updating the Custom Reports Schedules in Projects/Shells and Project/Shell Templates
You can update schedules in project/shell templates and existing projects/shells from the Custom Reports Schedule feature. You can create up to five Custom Reports Schedules for each report in a destination project/shell.
To update a schedule in projects/shells or templates:
- Go to the Company Workspace tab, and switch to Admin mode.
- In the left Navigator, select Templates, and then select Shells.
- Open the applicable template.
- In the left Navigator, select Reports, and then select Custom Reports Schedule.
- In the Custom Reports Schedule log, select the checkboxes for the applicable reports.
- In the toolbar, select Update, and then select one of the following:
- To update specific projects/shells, select Shells. In the Update Shells dialog box, select the applicable shells, and then select Update. When the confirmation message appears, select Yes to continue.
- To update all projects/shells, select All Shells. When the confirmation message appears, select Update.
- To update specific project/shell templates, select Shell Templates. In the Update Shell Templates dialog box, select the applicable templates, and then select Update. When the confirmation message appears, select Yes to continue.
- To update all project/shell templates, select All Shell Templates. When the confirmation message appears, select Update.
If the report does not exist in the destination, the system adds it and creates the schedule.