Activity Manager
Activity Manager [Activity Sheet]
| This setting: | Allows users to: |
|---|---|
| Send Data | Send data from an Activity Sheet |
| Get Data - Current and Baseline | Receive data in an Activity Sheet for the current and baseline projects |
| Get Data - Current Only | Receive data from an Activity Sheet for the current project |
| Modify - Current and Baseline | Modify Activity Sheets for the current and baseline projects |
| Modify - Current Only | Modify Activity Sheets for the current project |
| View - All | View all Activity Sheets |
| View - Current | View the Activity Sheet for the current project |
| Full Access |
|
| Create Manual Activity Sheets | Create Activity Sheets |
Activity Manager [OBS Sheet]
| This setting: | Allows users to: |
|---|---|
| Create and Add Users to Project |
|
| Create | Create OBS Sheet |
| Modify | Modify OBS Sheet |
| View | View OBS Sheet |
| Hide Audit Log | Hide the audit log for the OBS Sheet |
Activity Manager [Rate Sheet]
| This setting: | Allows users to: |
|---|---|
| Full Access | Create and view Rate Sheets |
| Create | Modify Rate Sheets |
| View | View Rate Sheets |
Activity Manager [WBS Sheet]
| This setting: | Allows users to: |
|---|---|
| Modify | Modify Work Breakdown Structure (WBS) Sheets |
| View | View WBS Sheets |
| Hide Audit Log | Hide the audit log for the WBS Sheet |
| Create Manual WBS Sheet | Create WBS Sheets |
Activity Manager [Custom Calendars]
| This setting: | Allows users to: |
|---|---|
| Create | Create a custom calendar |
| Modify | Modify a custom calendar |
| View | View a custom calendar |