SYS P6 Activity Constraint
Type: String
Size: 50
Input Type (Input Method): Pull-down Menu (Drop-down list)
Use on: The Data Elements (DEs) must be placed in a Shell Business Process, and the Activity Sheet must be located in the same Shell.
Description: To create DEs that map to Activity Constraint fields in P6.
The user cannot add new data set values, edit, or remove the existing data set values.
Category: System
Dataset:
- Start On
- Start On or Before
- Start On or After
- Finish On
- Finish On or Before
- Finish On or After
- As Late As Possible
- Mandatory Start
- Mandatory Finish
Default Value: None.
The user has the ability to set default to any value.
The user cannot add new data set values or edit or remove the existing data set values.