SYS P6 Activity Constraint

Type: String

Size: 50

Input Type (Input Method): Pull-down Menu (Drop-down list)

Use on: The Data Elements (DEs) must be placed in a Shell Business Process, and the Activity Sheet must be located in the same Shell.

Description: To create DEs that map to Activity Constraint fields in P6.

The user cannot add new data set values, edit, or remove the existing data set values.

Category: System

Dataset:

  • Start On
  • Start On or Before
  • Start On or After
  • Finish On
  • Finish On or Before
  • Finish On or After
  • As Late As Possible
  • Mandatory Start
  • Mandatory Finish

Default Value: None.

The user has the ability to set default to any value.

The user cannot add new data set values or edit or remove the existing data set values.