uuu_finish_baseline[1...10]

Data Definition: Date Picker

Form Label (Field Label): Baseline[1...10] Start

# of Characters: Not applicable

Where to use it:

  • Schedule Activity Attribute Forms
  • Schedule Sheets
  • Resource Assignment Attribute Forms

Use this element for: Displaying the baseline finish date of a project phase on a schedule sheet.

This is one element of a set that includes:

  • uuu_start_baseline[1...10]
  • uuu_duration_baseline[1...10]

    Note:

    You must include all three of these elements on the form for the baseline function to work correctly.

As the designer, you can assign a name to the baseline; for example, “Baseline Electrical.”