% Earned Calculation Method option is Lead resource updates Activity and other resources
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % complete updates % earned
- % Complete Calculation Method option = Lead resource updates Activity and other resources
- % Earned Calculation Method option = Lead resource updates Activity and other resources
then this data entry method scenario results:
| Activity or Resource | Data Element | Data Entry Method |
|---|---|---|
| Activity | ||
| Activity % Complete |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
|
| Earned Progress |
Calculated (read-only) Same as Activity % Complete |
|
| Resource | ||
| Progress Quantity |
Manual entry. (Only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on (Leader Progress Quantity / Leader Quantity) * Resource Quantity |
|
| Earned Progress |
Calculated (read-only) Same as Progress Quantity |
|