Oracle Primavera P6 EPPM Adapter Restrictions
Note the following Oracle Primavera P6 EPPM Adapter restrictions.
- The adapter does not support deleting data in P6 EPPM.
- It does not support the synchronization of spread values in a project schedule.
- It supports synchronization of only the following business objects in P6 EPPM:
- Global Data: Calendar, Rates, Resources, Roles
- Project Data: Activity, Assignments, Calendar, Project Header, Rates, Relationships, Resources, Risks, Roles, Tasks, WBS
- User-defined Fields (UDFs)
- Codes
Note:
There are overall service limits for Oracle Integration. A service limit is the quota or allowance set on a resource. See Service Limits.