Activity links determine the dependencies between the activities in Oracle Field Service.
To add an activity link:
1. Navigate to Configuration > General > Link Templates.
2. Click Add New.
3. Enter the General Settings, Time interval between activities, Link for the first activity, and Link for the second activity for W1AS_AfterStart. Click Add.Work Management Master Configuration page Main tab showing the Master Configuration Details.
Work Management Master Configuration page Main tab showing the Master Configuration Details.
4. Repeat the previous step for W1AF_AfterFinish.
Work Management Master Configuration page Main tab showing the Master Configuration Details.
Work Management Master Configuration page Main tab showing the Master Configuration Details.