Recording Emergency Operations
The new emergency sheet is automatically populated with Start and Finish dates. The Start date is the current date/time; the Finish date is defined as the Start date plus a predefined standard event duration.
Note: The duration is set to four hours in the product environment.
The sheet opens with the Steps tab active, real-time mode enabled, and recording on. If the Viewer is open, it transitions to real-time mode also. You can begin recording steps as described in the next section.
To record emergency switching operations, complete these steps:
1. Start a new emergency sheet as described in the previous section.
2. Create the steps by selecting assets in the Viewer window and selecting operations from the Control Tool. The process of adding recorded steps for emergency sheets is the same as for planned sheets in real-time mode. See “Adding Recorded Steps to a Switching Sheet” for details.
Once an action is completed in the Control Tool, the following occurs:
The status of the recorded step is set to Completed.
The Executed By field is populated with your user ID.
The Completed Date field is populated with the date and time shown on the Control Tool or the current time if a Control Tool date/time value is not specified.
Instructed actions use the date/time specified from the Control Tool to populate the Instructed Date field. If no Control Tool date/time value is specified, then the current time is used to populate the Instructed Date field.
Any outages created by completing steps in Real Time that are associated to an Emergency switching sheet will be classified as Real Outages and not Planned Outages. These Real Time step completions can occur from the Control Tool or from Web Switching Management.
3. When you have completed all emergency steps, click the Tracking/Audit Log tab and set the sheet state to Completed by clicking the Complete button. The Confirm State Transition dialog box will open; click Yes to confirm the completion or click No to close the dialog box without completing the sheet. The Finish Date may be updated, if necessary.
Optional: Add a comment in the text field to the right of the Complete button.
Note: Changes can no longer be made to the switching sheet while it is in the Completed state.