Changing Publish/Non-Publish or Default ERT Information
If you have the accessibility of the Storm Management estimates turned off, you can revise the default ERT, or you can change from publishing the default ERT to not publishing it or vice versa, without having to first turn the accessibility back on. To do this, complete these steps:
1. Do one of the following:
Click the ERT Override button on the toolbar, or
Select ERT Override... option from the System menu. The ERT Override dialog box opens.
2. If you want to update the ERT Override for a zone, click into the ERT Override cell of the applicable row, click the Date/Time button.
3. Select a date and time, then click OK.
4. Click out of the ERT Override cell and into a different cell to ensure the ERT Override time is saved.
5. Check or uncheck the Publish Projections check box for the applicable row.
6. Click OK. The following occurs:
The ERT Override dialog box closes.
The default ERT is published and/or revised if the Publish Projections check box was checked, or
The default ERT is not published if the Publish Projections check box was not checked.