3.2.15.1 Holiday Treatment for Disbursement/Payment/Revision/Maturity Schedules
You also have the option of specifying holiday handling preferences if the maturity date
of a contract falls on a holiday. You can select one of the following options if either
the schedule date or the maturity date falls on a holiday:
- Ignore the holiday
- Specify preferences for the movement of the maturity date
Table 3-8 Holiday Preferences
| Field | Description |
|---|---|
| Schedule Movement | If you have indicated that a currency holiday should not be ignored for the contract, you need to specify whether the schedule date/maturity date should move forward to the next working day or move backward to the previous working day.
Check with the appropriate field to indicate your preference. |
| Move Across Months | If you have chosen to move the schedule date/maturity date of a contract falling due on a currency holiday, either forward or backward to a working day and it crosses over into a different month, the schedule date/maturity date is moved to the next month only if you indicate so in this field.
Select this field to allow movement of schedule date/maturity date of the contract across months. Keep it deselected to indicate that the loan should mature/schedule should be paid within the same month on the last or first working day of the month, depending on whether the schedule date/maturity date is over the month-end or the beginning of the month. Notes: You are also be prompted to specify holiday handling preferences in the following circumstances:
|
| Cascade Schedules | The due date arrived at by the holiday treatment is considered as the start date for the due dates for the subsequent schedules. |
| Apply Payment Holiday Treatment: | When this option is selected, the system considers the holiday parameter defined for payment schedules.
The derived Pay By Date also considers this holiday preference. |
Parent topic: Holiday Preferences