10.3 Scaling Up Dynamic Cluster

This topic provides systematic instructions to scale up dynamic cluster capacity.

To scale up the insufficient capacity of the dynamic cluster, the user can add dynamic servers on demand.
  1. Navigate to the FCUBSDomain left panel.
  2. Click on the Environment drop down option and then click on the Clusters.
    Summary of Clusters screen displays.

    Figure 10-2 Summary of Clusters- TBD Redwood



  3. Click on the FCUBSCluster.
    Settings for FCUBSCluster screen displays.

    Figure 10-3 Settings for FCUBSCluster- TBD Redwood



  4. Click on the Configuration tab and then click on the Servers tab.
  5. Change the Maximum Number of Dynamic Servers to 8 and then click on the Save button.

    Figure 10-4 Summary of Dynamic Clusters



  6. Navigate to the Change Center left panel and click on the Activate changes.
    After activation, 4 new Dynamic Servers are added to the Dynamic Cluster.

    Figure 10-5 Summary of Dynamic Clusters - Change Center



  7. Start the 4 new Dynamic Servers and it doubles the capacity of the dynamic cluster.