3.3 Data Take on

This topic explains the process of actual taking on of the data.

This topic involves the actual taking on of the data into the system using the live database created and is a two step process:
  • Take on of information
  • Verification of the information taken on

Take on of information

In the case of a manual take on, this step would involve the manual entry of the information into the system. This information could include static and transaction information. The data entry will be done by the end users with the Oracle Financial Services Software Limited consultants assisting them in the same. The data conversion documents prepared during the data preparation exercise will be used here.

In the case of an automated take on operation, the conversion program is run during this stage which will bring the data into the system. A manual check of the data imported through reports can be carried out notwithstanding the fact that the reliability of the conversion program was tested during the earlier step. The reports listed in the above table can be used for checking. This verification exercise is to be done jointly by the client and the implementation team.

On successful completion of the checking exercise, a sign off of the data conversion milestone is done. The live database, data conversion test database and the conversion utility are backed up immediately.

Verification of the information taken on

The verification of the data entered can be carried out through the process of Data Callback. In this process the data imported is verified by manually checking the reports available in the system.

Given in the below table is a list of reports which could be used for the verification of the data entered.

Table 3-1 List of reports

Screen / Report / Inquiry Module Information verifiable Type of information
User Profile Report FMG Users NA
User Profile Details Report FMG Access rights of users NA
Entity Details Report FMG Details of entities set up in the system NA
Bank Maintenance FMG Details of banks set up in system NA
Broker Maintenance FMG Details of brokers set up in system NA
Holiday Maintenance FMG Details of holidays set up NA
Domicile Maintenance FMG Details of countries set up NA
Identification Maintenance FMG Details of identification types NA
Corporation Maintenance FMG Details of corporation types Static Information
Occupation Maintenance FMG Details of occupations NA
Investor Category Set- up FMG Details of investor categories set up NA
Fund Family Maintenance FMG Details of Fund Family Set-up NA
Fund Type Maintenance FMG Details of Fund Type Set- up NA
Fund Rule Report FMG Details of Fund Rules NA
View Load Details Inquiry AGY Load details set up NA
View Unit Holder Details Inquiry AGY Unit holder information NA
View Agents AGY Agent Details NA
View Agency Branch AGY Agency Branch Details NA
Standing Instruction Report FMG Details of Standing Instructions set up NA
Fund Activity Report AGY Details for transactions for a fund NA
View Unit Holder Balance FMG Details of Unit Holder Balances NA
Allocation Error Reports AGY Details of all the transactions failed during allocation NA
Transaction Summary Reports FMG Details of Transaction allocations Transaction Information
Fee / Incentive Report FMG Details of loads applied NA
UH Acknowledgement Report AGY Details of the Unitholders in the system NA
Fund Dividend Maintenance FMG Details of dividend set up information NA
View Dividend Payment Details FMG Details of dividend payout NA
Reinvestment Report FMG Details of reinvestments done NA
Annuity Failure Report FMG NA NA
Product Bank Suspense Report FMG NA NA
Annuity Forecast Report FMG NA NA
Capital Gains Tax Report FMG Details regarding the Capital Gains Taxes NA

Controls

The Data Take on should start only after the data to be taken on has been checked and signed off. While the client should verify the validity of the data, the implementation team should check the compatibility of the data with the system.

On completion of the testing of the data conversion program, a sign off should be obtained.

A sign off should be obtained on completion of import and verification of the data in the live databases. The live database and the conversion utility should be backed up.