7.1.5.6 Monthly Batch Scheduling

To schedule a Batch to run weekly, perform the following steps:

  1. In the Schedule Batch Page, click Monthly.
  2. Select the Batch /Batch Group Name.
  3. Select the Batch or Batch Name you want to schedule daily from the drop-down list.
  4. Enter a Schedule Name.
  5. Select the Start Date from which you want to run the Batch.
  6. Select the End Date till which you want to run the Batch.
  7. Select the Time at which you want to run the Batch every Month.
  8. Select the months in a year you want to run the Batch from the Select Months of the Year multi-select drop-down list.
  9. Select the day of the month that you want to run the Batch from the Select Day of the Month drop down menu.
  10. Click Schedule.