2.6 Adding Process Pipeline Dependencies

A process or a model can have any number of prerequisite operations to run before running the actual process or model and any number of post-requisites after running the process or model. Hence, STSA provides a configuration where you can maintain this list of prerequisites and post-requisites of all the selected processes and models for the composite pipeline that gets created while creating the analysis configuration and project.

To add process or model requisites:
  1. Login to STSA.
    The Workspace Summary page is displayed.
  2. In the Workspace Summary, Sandbox tab, launch the required workspace.
  3. Click the Context Menu representing the user name and then click Configuration Manager.
  4. Click Configure in the Define Process Pipeline Dependencies tile.
    The Requisite Management page is displayed.
  5. Select the process or model requisites, select Actions and then click Add and position the object.
  6. Click Save to save your changes.