Days Remaining calculated incorrectly based on most recent Aware Date for unsubmitted reports (Enhancement 29603540)
The Worklist > Open or New screen, displays the Days Remaining field is computed based on the Due Soon – Current date.
When managing unsubmitted reports for a case, Oracle Argus Safety calculated the value for Days Remaining based on the earliest known value for Due Date, instead of on the most recent Aware Date entered for the case.
A new common profile switch, Days Remaining Calculation in Worklist, is added in the Workflow node with the following options:
-
Use earliest due date of reports pending submissions (default)
When... ...populate Due Soon date based on: Auto-scheduling is done for the reports and the case contains scheduled reports.
Earliest due date of the report.
Auto-scheduling is done for the reports but the case does not contains any scheduled reports.
Latest aware date and duration as specified in the Due Soon Duration (in Days) for Worklist Calculation common profile switch.
Neither auto-scheduling is done for the reports nor likely to schedule a report.
Latest aware date and duration as specified in the Due Soon Duration (in Days) for Worklist Calculation common profile switch.
Auto-scheduling is not done for the reports but the reports are likely to be scheduled.
Earliest due date of the possible reports.
-
Use latest aware date
When... ...populate Due Soon date based on: Auto-scheduling is done for the reports, and may or may not contain any scheduled reports.
Latest aware date and duration as specified in the Due Soon Duration (in Days) for Worklist Calculation common profile switch.
Neither auto-scheduling is done for the reports nor likely to schedule a report.
Latest aware date and duration as specified in the Due Soon Duration (in Days) for Worklist Calculation common profile switch.
Auto-scheduling is not done for the reports but the reports are likely to be scheduled.
Earliest due date of the possible reports.