Schedule InForm data loads in Production

  1. After you select a study, click the Study Configuration icon Shows gear with pencil iconfrom the navigation bar. Then click the Clinical Data Model tab.
  2. Select Production from the Lifecycle drop-down at the top of the page.
  3. Click the Icon is two parallel vertical lines. Suspend icon.
  4. Install the model if it has not already been installed in Production.
  5. Select Production under Study Lifecycle in the table below.
  6. Select the Schedule Production Data Load checkbox to ensure that your frequency and start time settings get scheduled.
  7. In the Frequency in Minutes field, enter the number of minutes between automatic data loads. (Data loads do not start until the previous one completes.)
  8. In the Start Time with 24-hour Clock field, enter the hour and minutes in hh:mm format.

    Note:

    To ensure the data loads at the correct start time, do not enter a time too close to the current local time. To allow background processes to run, make sure that the time entered is a minimum of ten minutes into the future. If you enter a time that expires before the data load starts, the data cannot load until the specified time on the next day.
  9. Click Save.
  10. Click the Resume icon. The first scheduled data load starts at the specified start time. If you did not enter a start time, it starts immediately.

See InForm data isn't loading? for more information (if necessary).