Synchronizing Block Projected Revenues

Use this utility to ensure that the revenue summary tables are populated for either new blocks or existing blocks. This utility populates the revenue summary tables for blocks that do not have revenues populated yet and also corrects any possible discrepancies for blocks that already had revenues populated in their summary table.

  1. From the Toolbox menu, select Utilities, select Synchronization then select Block Projected Revenues.
    1. Property: Select or confirm property.

    2. From Date: Enter or select a start date.

    3. To Date: Enter or select an end date.

    4. Mode:

      1. Blocks without Revenue Summaries - use this option for blocks that have no revenues populated in the summary table yet.

      2. All Blocks - use this option to synchronize revenues for all blocks, including those that already have revenues populated in the summary table.

    5. Click Synchronize Block Projected Revenues.

Note:

During synchronization, you can stop the process; however, records that have already been populated won't be reverted.