Create the Central Designer study deployment

If you are migrating to the InForm 7.0.1 release, the Central Designer project for each study must be updated to Central Designer 7.0.

For on-prem installation, a new deployment must be sent to the InForm application to update each study. The purpose of this new study deployment is to upgrade the InForm study to use the latest rule engine. This new deployment package must reflect, at a minimum, an insignificant change (for example, move just one object in the workflow diagram in Central Designer) to trigger a new study version.

For more information, see the Central Designer User Guide.

Note: For each study being updated, make sure all the languages in the original study are selected.