Set dates for multiple documents
When you first enter a baseline date, Oracle Site Activate automatically makes the planned date the same. After a baseline date is entered, it cannot be changed.
- From your home page, click Planning.
- Select one or more documents for which you would like to set a date. To select all documents, click the box next to Investigator.
- Optional: (Optional) To remove an item from the list, click X to the right of it.
- Enter a baseline or planned date for the selected documents. Baseline date is the date by which you would like the activity to be completed; the default is the current date. Planned date is a new date to be entered as plans change. To enter a planned date only, delete the baseline date by clicking the X to the right of it.
- Click Done.
Parent topic: About documents