Running Analysis and Reviewing the Device Solution
Analysis refreshes calculation inputs, calculates target setpoints, applies the value precedence described earlier, validates low limits, and assigns a calculation status and message to each row.
1. Select Analysis.
2. Review each row with Ready or Review status.
3. Resolve or intentionally exclude rows with Blocked, No SCADA Setpoint, or Error status.
4. Confirm the Use setting for every intended and excluded device.
5. Scroll horizontally to review the values for all phases, including bandwidths and low limits, and the Calc Status and Message / Reason columns.
Editing Device Targets
Edit values in the applicable table columns: Use, Target Setpoint A/B/C, Bandwidth A/B/C, and Low Limit A/B/C. Review all changed values before creating the job. After rerunning Analysis, confirm that every intended edit remains correct.
In the Use column, select whether to include or exclude a device:
• Enable: The device can participate when its calculation result is executable.
• Disable: The device remains visible but is excluded from generated EVR steps.
Pre‑Job Review
Before selecting Create Job, verify all the following:
• The selected zones or regions match the approved operating scope.
• The reduction percentage, execution mode, restore mode, and device category are correct.
• The choice of immediate or scheduled execution is intentional, and scheduled dates are correct.
• The expected number and type of devices were fetched.
• The reason for each Blocked, No SCADA Setpoint, Error, or Disabled row is understood.
• All Review rows and operator-entered values are correct.
• Only intended devices have Use set to Enable.
• The displayed voltage unit is understood.
• Current DMS modes and any site-specific coordination requirements have been reviewed.
Note: Do not create the job solely because every visible row is Ready. Confirm the complete device population and the values in columns that are not currently visible.
Working with EVR Cases and Jobs
Saving an EVR Case
Save Case stores the current request and device solution as a reusable snapshot. Saving a case does not create an event, create a switching sheet, or execute controls.
1. Define the request, fetch devices, and run Analysis.
2. Review or edit the device rows.
3. Select Save Case.
4. Enter a note that identifies the operating purpose and any important assumptions.
5. Confirm the save.
Opening and Deleting Saved EVR Cases
From the File menu, select EVR Saved Solutions to review saved cases. The list can include the saved date, note, user, zones, reduction percentage, execution mode, and device category.
1. Select File, then EVR Saved Solutions.
2. Select a saved case and open it as a working solution.
3. Review the request and device rows.
4. Rerun Analysis when current SCADA values or operating conditions may have changed since the case was saved.
Opening a saved case does not execute EVR. Deleting a saved case removes only the saved snapshot; it does not delete events or switching sheets previously created from another working solution.
Creating an Immediate Automatic EVR Job
1. Set Execution Mode to Automatic and leave Schedule Window disabled.
2. Fetch devices, run Analysis, and complete the pre-job review.
3. Select Create Job.
4. Record the event and switching-sheet identifiers shown by the system.
5. Monitor Work Agenda and Switching until execution completes, fails, is canceled, or is stopped.
6. Verify actual device settings from current SCADA information.
Note: For an immediate Automatic request, Create Job can submit control steps without pausing for further review.
Creating a Scheduled Automatic EVR Job
1. Set Execution Mode to Automatic and enable Schedule Window.
2. Enter the Start Date and End Date and confirm the intended time zone.
3. Fetch devices, run Analysis, and complete the pre-job review.
4. Select Create Job.
5. Open the generated sheet and verify Scheduled Time values for reduction and restore blocks.
6. Monitor the Scheduled and Executing states and the final outcome during the scheduled window.
Note: For Automatic EVR, Create Job disables the licensed VVO and DERMS global modes before submitting the switching sheet. For scheduled EVR, this occurs when the job is created, not when the Start Date is reached. EVR does not retain the previous modes. Successful completion of a sheet containing EVR restore blocks sets the licensed modules to Manual. If execution fails, is aborted, or includes only reduction steps, verify and set the modes as required by local procedures.
Creating a Manual EVR Event
1. Set Execution Mode to Manual.
2. Fetch devices, run Analysis, and complete the pre-job review.
3. Select Create Job.
4. Open the event from Work Agenda and review the EVR Report.
5. When ready, use Generate Sheet from the EVR Report to prepare a review switching sheet.
Manual mode records the EVR request and device solution without submitting control work from the main tool.
Existing Events and Sheets
EVR associates the working solution with the identifiers of its event and switching sheet. When an event or sheet already exists for the solution, the application can reuse the existing record or warn that a sheet already exists instead of creating a duplicate. Read the displayed message and open the existing event or sheet before repeating Create Job or Generate Sheet.
Monitoring EVR Operations
Typical Life Cycle of an EVR Event
1. Request Definition and Analysis: The operator defines the scope and reduction, fetches devices, and reviews the calculated solution.
2. Event Creation: Create Job creates or reuses the Work Agenda event and associates the EVR solution with it.
3. Switching Sheet Generation: Automatic mode creates the sheet from the main tool. Manual mode waits for Generate Sheet from the EVR Report.
4. Immediate Submission or Scheduling: Immediate sheets are submitted at once. Scheduled sheets remain queued until a scheduled block is due.
5. Reduction Execution: Switching executes eligible device blocks and updates step, sheet, and DMS status.
6. Completion or Failure: The event and sheet reach terminal states when the generated execution work completes, fails, is canceled, or is stopped.
7. Restoration: Scheduled restore blocks execute at the configured time, or an operator later generates Pre-EVR or Nominal restore steps.
8. Audit and Review: The EVR Report and switching logs retain messages about the request, calculation, switching sheet, execution, and restoration.
Monitoring EVR in Work Agenda
EVR events are displayed in Work Agenda. Use the general event Status and the DMS Status together: Status identifies the Work Agenda life cycle, while DMS Status describes EVR progress.
Understanding the Status Layers