Verifying Operation of the Oracle ZFS Storage ZS5-2 Slide-Rails and CMA

Use the following procedure to verify the operation of the cable management arm (CMA) and slide rails for an Oracle ZFS Storage ZS5-2 controller.

Before You Begin

Ensure all rack anti-tilt devices are extended to prevent the rack from tipping forward when the storage controller is extended from the rack.

  1. Slowly pull the storage controller out of the rack until the slide-rails reach their stops.
  2. Inspect the attached cables for any binding or kinks.
  3. Verify that the CMA extends fully with the slide-rails.
  4. Push the storage controller back into the rack and verify that the CMA retracts without binding.
  5. Adjust the cable straps and the CMA, as required.