Source Mappings

Source mappings include explicit and adjustment period mappings. You can create explicit period mappings to ensure that the Data Management periods map correctly to the source system calendar periods. An adjustment period mapping is used only when you select the Include Adjustment Periods option when creating the data load rule.

The Source Mapping tab consists of two areas:

  • Master—Selects the source system and mapping type.

  • Grid—Defines the period mapping. The mapping can be defined only for periods defined on the Global Mapping. New Data Management periods cannot be created on this tab.

Note:

In Data Rules, you can choose between Default period mapping and Explicit Period mapping. If you choose Period mapping, then source periods are mapped based on the period key and previous period.

To create source mappings:

  1. On the Setup tab, under Integration Setup, select Period Mapping.

  2. Select the Source Mapping tab.

  3. In Source System, select the source system.

  4. In Mapping Type, select Explicit.

  5. Click Add.

  6. Enter the source system Period Name, and then click OK.

    Note:

    Period names cannot include spaces if used in a batch script.

  7. Enter the source system Period Key, and then click OK.

  8. Enter the source system Calendar, and then click OK.

  9. Enter the source system GL Period, and then click OK.

    The GL Period Number is prefilled based on the Period Name.

  10. Enter the source system GL Name, and then click OK.

  11. Optional: Enter a description for the mapping.

  12. Click Save.

To create source period mappings:

  1. On the Setup tab, under Integration Setup, select Period Mapping.

  2. In Period Mapping, select the Source Mapping tab.

  3. In Source System, select the source system.

  4. Click Add.

  5. Click Image shows Search button to select the source system Period Key, and then click OK.

  6. Click Image shows Search button to select the source system Calendar, and then click OK.

  7. Click Image shows Search button to select the source system Adjustment Period, and then click OK.

  8. Optional: Enter a description for the mapping.

  9. Click Save.

  1. Select Source Mapping.

  2. In Source System, select the source system.

  3. Click Add.

  4. In Mapping Type, select Budget.

  5. In Period Name, specify the period name.

    You can also click Image shows Search button to search for the period name.

    Note:

    Period names cannot include spaces if used in a batch script.

  6. Enter the source system Calendar, and then click OK.

    You can also click Image shows Search button to search for the calendar name.

  7. Enter the source system GL Period, and then click OK. You can also or click Image shows Search button to search for and select the General Ledger period name.

    The GL Period Number is prefilled automatically based on the Period Name.

  8. Optional: Enter a description for the mapping.

  9. Click Save.

Tip:

To delete a mapping, select the mapping, and then click Delete.