Plan Orchestration Processes
Use the Plan Orchestration Processes scheduled process to calculate planning dates and jeopardy scores.
When to Use
See the Replan Your Orchestration Process subtopic in Guidelines for Setting Up Orchestration Processes.
Privileges Required
- Plan Orchestration Processes (DOO_PLAN_ORCHESTRATION_PROCESSES_PRIV)
Specifications
Use these specifications when you run the scheduled process.
Specification | Description |
---|---|
Job Type | Scheduled or as needed. We recommend that you run this scheduled process at regular intervals. This way, you can process data without having to constantly run the process manually. |
Frequency | As needed. |
Time of Day | Any time. |
Duration | Varies depending on the parameters that you set when you run the scheduled process. |
Compatibility | You can run more than one instance of this scheduled process at the same time. However, to avoid conflicts, we recommend that you run only one instance at a time. |
Parameters
Use these parameters to filter the data that the scheduled process will look at.
Parameter | Description |
---|---|
Orchestration Process Number | Specify a value that uniquely identifies the orchestration process that you need to update, such as 300100541247223. |
Requested Fulfillment Start Date Requested Fulfillment End Date |
Filter the data that you want to process according to the requested fulfillment dates on the order line. |
Customer | Select a customer, such as Computer Service and Rentals. |
Item | Select an item, such as AS54888. |
Item Category | Select an item category, such as Computers. |
Process Name | Select the name of an orchestration process, such as ShipOrderGenericProcess. |
Process Class | Select the name of an orchestration process class. For example, if you select Ship Order Class, then the scheduled process will update the plans for all orchestration processes that are in the Ship Order Class. |
Replan Instances |
Specify how to calculate the planning dates for each step in the orchestration process. Select a value.
For details about planning dates, see the Plan Your Dates subtopic in Guidelines for Setting Up Orchestration Processes. |
Business Unit | Select a business unit, such as Vision Operations. |
Warehouse | Select a warehouse, such as Denver Manufacturing. |
All parameters are optional.
No special combinations are required.
For important details, see Guidelines for Using Scheduled Processes in Order Management.