Split or Substitute Fulfillment Lines
Promising might split an order line across warehouses, substitute items, or dates.
Promising splits an order only if the Allow Partial Shipments of Lines attribute on the line contains Yes.
Split a Warehouse
Promising splits a line across warehouses only if the Requested Ship From Warehouse attribute on the original order line doesn't contain a value.
Promising uses the sourcing rule for the order line to determine which ship from warehouses it can consider.
If Promising splits across warehouses, then each order line that the split creates contains a different value in the Expected Ship From Warehouse attribute.
Substitute the Item
Promising substitutes one item for another item only if the Allow Substitutions attribute on the order line contains Yes.
If Promising splits lines when it substitutes the item, then each order line that the split creates contains a different value in the Available Item attribute.
Assume the order line has a quantity of 100 for the AS54888 desktop computer, the AS6000 is a substitute for the AS54888, 80 units are available for the AS54888, and 50 for the AS6000. The Check Availability action will split the order line into lines x and y:
-
Line x will have 80 units for the AS54888
-
Line y will have 20 units for the AS6000
Consider Dates
Promising creates two dates when it splits availability across dates.
- The first date contains the quantity that's available on the requested date.
- The second date contains the remaining quantity that's available for the same item and from the same organization.
Assume the order line has a quantity of 100 for the AS54888 desktop computer, 80 units are available on March 1, and 40 units are available on March 10. The Check Availability action will split the order line into lines x and y:
- Line x will have 80 units and an expected delivery date of March 1.
- Line y will have 20 units and an expected delivery date of March 10.
Consider Lead Times
Promising examines lead time when it determines how to split an order line.How You Fulfill the Item | Lead Time Attributes That Affect Promising |
---|---|
Manufacture |
|
Purchase |
|
Transfer |
|
Drop Ship |
|
- Go to the Product Information Management work area.
- Click Tasks > Manage Items.
- Search for, then open your item for editing.
- Click Specifications > Planning.
- In the Lead Times area, set the values for the attributes, as necessary.
- Preprocessing Days
- Postprocessing Days
- Processing Days
- Variable
- Fixed
Other Lead Times That Affect Promising
Make sure you also consider your other setups.
Other Fantastic Lead Times | And Where to Find Them |
---|---|
Cumulative manufacturing lead time and cumulative total lead time in an available-to-promise rule | See the section that starts with Lead Times Usage in Oracle Manufacturing. Also see Promising Modes for ATP Rules. |
Supplier Lead Time | See the Manage Sourcing Rules section in Set Up Drop Ship in Order Management |
Transit Lead Time | Transit Times |