Upgrade Guide for DB2 UDB for z/OS > Upgrading a Database from the Mainframe > Executing the Upgrade on the z/OS Host (Phase 1 of 2) >
Running Load Jobs on the Target Database
Perform the following procedure to run load jobs on the target database. To run loads to the target database
- If you are not on the Siebel Upgrade Main Menu, enter the following command:
TSO SBLUPG78
- Select option 5: RUN UPGRADE / POST-UPGRADE MAINTENANCE.
The Siebel Upgrade Job Submission Menu for your upgrade path appears.
- For Siebel Business application upgrades, the panel ID is SBLRUNHP.
- For Siebel Industry application (SIA) upgrades, the panel ID is SBLRUNFP.
- Select option 3: LOAD TARGET.
This places you in edit mode for dataset DSNHLQ.SIEBEL.INSTALL.JCL(SUBLOAD).
- Run the job using the JCL in dataset DSNHLQ.SIEBEL.INSTALL.JCL(SUBLOAD).
This job automatically submits all the unload job streams referenced in dataset DSNHLQ .SIEBEL.EXEC(@DDLIMPL) .
This submits the Load job streams. The number of upgrade Load jobs varies by upgrade path. If you selected Siebel-Scheduled Mode, this job is logged (as Completed Successfully or Failed) to the target Siebel log table: TARGET_TABLEOWNER .TMP_SBLLOG_TAR .
- Verify job ran successfully, RC=
0 or RC=4 .
Jobs with an ABEND (end abnormally) U99 or U099 message are jobs that failed.
NOTE: You must fix any failed jobs before proceeding with the upgrade. For information on restarting failed jobs, see Restarting Failed Jobs on the Mainframe.
- After submitting the job, enter
cancel on the command line or press PF3 to save changes.
- View the job status.
For information on how to view job status if you selected Siebel-Scheduled Mode, see Viewing the Siebel Job Log Status.
Once all Load jobs have completed successfully, continue with the upgrade.
|