Table 17. eGanttChart Busy Free Time Applet User Properties
|
|
|
Major Time Unit |
Day |
Major time unit in the X-axis of the Gantt chart. The possible values are Day, Week, Month, and Year. |
Minor Time Unit |
Hour |
Minor time unit in the X-axis of the Gantt chart. The possible values are Hour, Day, Week, and Month. The possible combinations of (major,minor) time units are (Day,Hour), (Week,Day), (Month,Day), (Month,Week), and (Year,Month). |
X-BC |
Action (Busy Free Time) |
Business component for the X-axis of the Gantt chart. |
X-Color Field |
Priority |
Cells of the Gantt chart can be colored differently. This user property specifies which field in the X business component determines the coloring. For the field that you choose, make sure there is a corresponding LOV defined. See X-Color LOV Name for details. |
X-Color LOV Name |
ACTIVITY_PRIORITY |
LOV that defines the possible values of the field chosen for X-Color Field. From this LOV, you can determine the Language Independent Code (LIC) of the field value. |
X-LOV Map |
#1-ASAP#2-High# 3-Medium# |
Defines the LIC of the LOV values that can be mapped to colors. |
X-Color Map |
#GanttChartRed #GanttChartBlue #GanttChartGreen# |
Defines the colors of the different values of the LIC. The values must be in the same order as in X-LOV Map. For example, 2-High maps to GanttChartBlue. The values of X-Color Map are the style sheet classes defined in Gantt.css. |
X-Date InvokeMethod |
SetGridBeginEndDate |
Maps to an internal X-business component method to calculate the date-time range for the X-business component data. Do not modify this. |
X-Display Constraint Map |
08:00:00#17:00:00 |
Applies only when the minor time unit is Hour. Instead of displaying a 24-hour interval in the Gantt chart, this user property defines the lower and upper bounds of the time displayed in the Gantt chart. |
X-Display Duration |
30 |
Specifies the time increment for each cell in the Gantt chart. The unit is Minutes. |
X-DrillDown Field |
Description |
Specifies the field in the X business component on which you can drill down. A corresponding Drilldown Object must be configured for the applet in Siebel Tools. |
X-End DateTime Field |
Planned Completion |
Field in the X business component that specifies the end of the datetime range. |
X-Join Field |
Primary Owner Id |
Field in the X business component that links it to the Y business component. This is used in a search specification if X-Join InvokeMethod is not specified. |
X-Join InvokeMethod |
SetEmployeeList |
Maps to an internal X business component method to link the Y and X business components. Do not modify this. |
X-Num Slots |
3 |
Specifies the number of "slots" for a given cell. For example, you might have conflicting activities that start and end at the same time. If X-Num Slots is 3, the cell that represents this time range can be split into a maximum of three slots to contain the conflicting activities. |
X-Sort Spec |
Owner Last Name |
Specifies the sort specification for the X business component. |
X-Start DateTime Field |
Planned |
Field in the X business component that specifies the start of the datetime range. |
X-Tooltips 1 |
Planned |
First control that is displayed in the tooltip. |
X-Tooltips 2 |
Planned Completion |
Second control that is displayed in the tooltip. User properties can be defined to extend this to X-Tooltips n. |
Y-BC |
Employee (MM) |
Business component for the Y-axis of the Gantt chart. |
Y-BC ViewSet Size |
7 |
Maximum number of records for the Y-axis. |
Y-Constraint |
None |
Search specification for the Y business component. NOTE: By default, the Y business component in the base Gantt chart class does not have any search specification defined. If it is not explicitly defined here, the Y business component is constrained by a link in a parent/child relationship.
|
Y-DrillDown Field |
Id |
Source field for the Y drilldown. |
Y-DrillDown View |
All Employees across Organizations |
Destination view of the Y drilldown. This can be modified. |
Y-Join Field |
Id |
Field in the Y business component that links it to both the X and Z business components. |
Y-Label |
Employee |
Label for the Y-axis. |
Y-Legend |
Full Name |
Field in the Y business component that is displayed in the Gantt chart. |
Y-SortSpec |
Last Name |
Sort specification for the Y business component. |
Z-BC |
Schedule |
Business component for the Z-axis of the Gantt chart. Acts as a layer painted on the Gantt chart before the X-axis is constructed. For example, each employee has a working schedule of Monday through Friday, 8:00 to 17:00. The Gantt chart is painted white where there is a schedule and gray where there is no schedule. The activity cells are drawn on top of this schedule layer. The Z business component determines the state of a cell:
- GanttStateNone: No schedule
- GanttStateOff: A schedule exists
- GanttStateOn: Coloring of the cell controlled by
X-Color Map
|
Z-Date InvokeMethod |
SetGridBeginEndDate Time |
Maps to an internal Z business component method to calculate the datetime range for the Z business component data. Do not modify this. |
Z-End DateTime Field |
End DateTime |
Field in the Z business component that specifies the end of the datetime range. |
Z-Join Field |
Employee Id |
Field in the Z business component that links to the Y business component. This is used as a search specification if Z-Join InvokeMethod is not specified. |
Z-Join InvokeMethod |
SetEmployeeList |
Maps to an internal Z business component method to link the Y and Z business components together. Do not modify this. |
Z-Start DateTime Field |
Start DateTime |
Field in the Z business component that specifies the start of the datetime range. |