Siebel Field Service Guide > Preventive Maintenance >

Preventive Maintenance Overview


The Preventive Maintenance Engine can automatically generate preventive maintenance (PM) service requests and actions (or activities), triggered by elapsed time, asset usage, measurement thresholds, or events (see Figure 21):

When a PM activity is required, Field Service creates service requests and detailed activities. Figure 21 shows the process of the Preventive Maintenance Engine, which is as follows:

  1. Run the PM Engine for an asset or an agreement.
  2. Select the PM Plan for the asset or for the entitlement's assets.
  3. For each trigger, if conditions require an action, create service requests or activities, then run the PM Engine. If conditions do not require an action, run the PM Engine.
  4. Continue the process until all necessary service requests and activities have been created.

Figure 21.  Logic of the Preventive Maintenance Engine

Click for full size image


 Siebel Field Service Guide 
 Published: 21 April 2003