Importing Scenarios to the Production Environment


This topic describes how to export the Integration scenarios from the Oracle Data Integrator development environment and import the scenarios into the production environment. It also describes how to modify scenario variables in the production environment. For detailed information on importing and exporting Oracle Data Integrator objects, see Oracle® Fusion Middleware Developer's Guide for Oracle Data Integrator.

This task is a step in Process of Implementing the Integration in an Oracle Data Integrator Production Environment.

When Oracle Data Integrator scenarios are generated in a development environment, the default values of the global and project variables used in the scenarios relate to the development environment. When Oracle Data Integrator is then deployed in the production environment, these default values might not apply.

To ensure that the values of the variables used in scenarios are appropriate when scenarios are transferred to the production environment, use one of the following methods:

  • Change the values of the Global and Project variables in the development environment to the correct values for the production environment, and then generate the scenarios. For more information, see Configuring Integration Variables.
  • Manually modify the Global and Project variables used in the scenarios in the production environment. For more information, see Modifying Scenario Variables in the Production Environment.
  • Pass the correct values of the Global and Project variables for the production environment to Oracle Data Integrator each time a scenario is run. Oracle Data Integrator overrides the default value of the variable with the value that is passed.

    This option is available only if you have installed the Oracle Data Integrator Standalone Agent and can run scenarios from the command line. For additional information, see Oracle® Fusion Middleware Developer's Guide for Oracle Data Integrator 11g Release 1.

Transferring Scenarios Between Repositories

The following procedure describes how to export scenarios from the Oracle Data Integrator development environment and import the scenarios into the production environment.

To transfer scenarios between repositories

  1. Perform the following steps to export the scenarios from the development environment work repository:
    1. After generating the Integration scenarios in a development environment as described in Generating Scenarios for Integration Packages, open the Operator navigator and select Scenarios.
    2. Right-click the scenario that you want to export, then select the Export menu item.
    3. In the Export Directory field, enter the path to the directory where you want to export the scenario, then click OK.
    4. Repeat Step c for each scenario that you want to export.
  2. To import the scenarios into the production environment work repository, perform the following steps:
    1. In the production environment, start ODI Studio, and connect to the ODI work repository.
    2. Open the Operator navigator, right-click Scenarios, then select the Import Scenario menu item.
    3. In the File import directory field, enter the name of the file import directory. Specify the name of the directory that you exported the scenario to in Step 1.
    4. Select the files that you want to import, and then click OK.
    5. Click Yes to continue the import if a warning message appears stating that you are about to delete or replace objects.

      When the import process is completed, a list of the imported objects is displayed.

Modifying Scenario Variables in the Production Environment

You must update the variables in the scenarios that are imported to the production environment by replacing any variable value that contains information specific to the development environment with the corresponding values for the production environment. The following procedure describes this task.

To modify scenario variables in the production environment

  1. In the Operator navigator, navigate to Scenarios, Scenario Name, Variables, Variable Name

    where:

    • Scenario Name is the name of the imported scenario
    • Variable Name is the name of the variable to be updated
  2. In the Scenario Variable editor, change the value in the Default Value field to the appropriate value for the production environment.
  3. For each of the imported scenarios, repeat Step 1 and Step 2 for the following variables:
    • FINS_BIB_Default_Organization
    • FINS_BIB_EIM_ErrorFlags
    • FINS_BIB_EIM_SQLFlags
    • FINS_BIB_EIM_TraceFlags
    • FINS_BIB_Enterprise_Server
    • FINS_BIB_Gateway_Server
    • FINS_BIB_Log_Path
    • FINS_BIB_Organization
    • FINS_BIB_Password
    • FINS_BIB_Siebel_Path
    • FINS_BIB_Siebel_Server
    • FINS_BIB_Username