About Creating a Schedule for the Upgrade


Develop a plan for your upgrade based on the objectives and constraints for your deployment.

If you are migrating multiple languages from a prior version, plan extra time for the repository merge process. The expected merge time can increase with the number of languages in the repository. You also might have to plan for additional installation-related tasks.

The following procedures can reduce the time required for your upgrade:

  • Run selected processes in advance of the upgrade.

    Certain preupgrade tasks can be run at any time prior to the upgrade. These procedures can be performed in advance either for testing purposes or to accommodate downtime constraints.

    Examples of procedures that can be performed by a database administrator in advance of your upgrade include Preparing the Storage Layout of the Schema.

  • Apply additive schema changes to the production database ahead of the target database in-place upgrade. See About Siebel Additive Schema Upgrade Changes.
  • Prepare select processes to run in parallel.

    If a large table such as S_EVT_ACT is partitioned, it can run in parallel by transferring shipped statements into the numbered SQL statement.

Do not start a new development effort until after the new version has been rolled out.