Preparing the Site for System Installation
Load-Bearing and Handling Precautions
Power and Electrical Requirements
Temperature and Humidity Requirements
Clearance for Service and Aisle Requirements
Mounting the Chassis in a Rack
Secure Installation Requirements
Hazardous Conditions Precaution
Shipping Crate Physical Specifications
Up to four Sun Blade 6000 chassis can be installed in a 1000-42 rack, with the exceptions shown in the following list.
The following configurations are supported by MPS:
Worst case consumption (32A), 60A-3 phase: one Sun Blade 6000 chassis
One 32A-3 phase – three Sun Blade 6000 chassis
Two 60A-3 phase – three Sun Blade 6000 chassis
Two 30A-1 phase – one Sun Blade 6000 chassis