5.1 Power On Task Map

Table 5.1 describes the steps for powering on Oracle Virtual Compute Appliance X3-2 at your site.

Table 5.1 Steps for Powering On Oracle Virtual Compute Appliance X3-2

Step

Description

Links

1

Review the safety precautions, guidelines, site checklists, and site requirements.

Section 5.3.1, “Review Safety Guidelines”

2

Perform preliminary checks before connecting the power cords.

Section 5.3.2, “Inspect Oracle Virtual Compute Appliance X3-2”

3

Verify the hardware by visually inspecting the system.

4

Connect the F1-15 Director switch and Oracle Switch ES1-24 switches. Also connect a workstation with monitor to the Oracle Switch ES1-24.

Section 5.2, “Before Initial Power On”

5

Supply rack power, and perform the power-on self-test device checks.

Section 5.3.3, “Connect the Power Cords”

6

Switch on the two power distribution unit (PDU) circuit breakers located on the rear of the main PDU (PDU A).

Section 5.3.4, “Power On Oracle Virtual Compute Appliance X3-2”

7

Power on the management nodes.

8

Wait 3 to 5 minutes and then connect to Oracle Virtual Compute Appliance X3-2.