Copying Menu Item Links from a Master Cost Center to Assigned Cost Centers

  1. Click Maintenance, clickScheduler, and then click Create Job.
  2. Select Menu Item AutoLink as the Job Type, and then click OK.
  3. Select the Start Date and Start Time to run the job.
  4. To run the job only once at the selected date and time, select Run Once.
  5. To run on a regular basis, select Periodically, every, and then enter the frequency to run the job.
  6. Click Save.