Previous  Next          Contents  Index  Navigation  Glossary  Library

Lead Time Offsetting Computations

Dynamic lead time offsetting offsets dates in two steps, computing total lead time and offsetting the date by total lead time. Total lead time contains both fixed lead time and the quantity-dependent portion of lead time. Preprocessing lead time is also included for discrete items.

To compute the total lead time for discrete items use the following equation:


Compute the total lead time for repetitive items using the following equation:


Offset the date by total lead time using the following equation:


Example

Master Scheduling/MRP uses dynamic lead time offsetting to compute a planned order release date. Master Scheduling/MRP computes total lead time and then uses the workday calendar to calculate the planned order release date.

Suppose your MRP plan produced a requirement for 100 discretely manufactured assemblies on March 12 and the following information exists for that assembly:

Master Scheduling/MRP first computes the total lead time as follows:


Suppose your organization's workday calendar has a workday pattern with five days on and two days off. Workdays 1 - 5 are March 1 - 5. Saturday and Sunday, March 6 and 7, are off. Workdays 6 - 10 are March 8 - 12.

Master Scheduling/MRP then calculates the planned order release date as follows:


Convert planned order requirement date to a workday (using your organization's workday calendar).


Finally, determine the start date.


See Also

Overview of On-hand and Availability

Material Requirements Planning


         Previous  Next          Contents  Index  Navigation  Glossary  Library