Schedule Field

Yes Include this resource when scheduling an operation from a job or repetitive schedule and calculating manufacturing lead time for the assembly.
No default Do not include scheduling the operation or calculating the lead time.
Prior Include this resource when scheduling a job or schedule by backward scheduling the previous operation from the end of this resource. Use this option when setup resources can work in parallel with previous operations. The lead time is calculated the same way Work in Process schedules the job or repetitive schedule.

Next Include this resource when scheduling a job or repetitive schedule by forward scheduling the next operation from the start of this resource. Use this option when the teardown of the current operation can overlap with the execution of the next operation. The lead time is calculated the same way Work in Process schedules the job or repetitive schedule.