Yes
| Include this resource when scheduling an operation from a job or repetitive schedule and calculating manufacturing lead time for the assembly.
|
No
default
| Do not include scheduling the operation or calculating the lead time.
|
Prior
| Include this resource when scheduling a job or schedule by backward scheduling the previous operation from the end of this resource. Use this option when setup resources can work in parallel with previous operations. The lead time is calculated the same way Work in Process schedules the job or repetitive schedule.
|