Usage Rate
Usage rate represents the amount of resource required to build one unit of an item at a particular operation. The usage rate is stated the unit of measure you specify when defining the resource in Oracle Bills of Material. In the Resource Requirements Snapshot Example, building one unit of C at operation 20 requires 8 hours of D1, R2.
Attention: Oracle Capacity only plans routing-based capacity for resources that have a unit of measure that is time-based and can be converted to hours.
See Also
Basis