Resource Requirements from Oracle Bills of Material

The following table illustrates the resource requirements loaded by the Snapshot from Oracle Bills of Material. These are used by routing-based CRP to calculate resource requirements for planned orders and repetitive schedules.

Item Op Seq Dept Resource Runtime Qty Basis Resource Offset
A 10 D3 R1 4 Item 0
A 20 D3 R2 4 Item 0.5
B 10 D2 R1 6 Item 0
B 20 D2 R2 6 Item 0.5
C 10 D1 R1 8 Lot 0
C 20 D1 R2 8 Item 0.5