MPS Plan Generation

You can launch the planning process for an MPS plan from a master demand schedule. This generates an MPS plan for all your MPS planned items. Oracle Master Scheduling/MRP and Supply Chain Planning also plans any MRP planned items that have an MPS planned component. This ensures that all derived demand is correctly passed down.

Once you have generated an MPS plan, you can make a copy of the plan that is identical to the original. You can then view, implement, and replan either copy, discarding the altered plan at any time and preserving the original data.

Supply Chain Planning users can also generate DRP and supply chain MRP and MPS plans. Supply Chain Planning users should refer to MPS Plan Generation in Supply Chain Planning for further information.

See Also

Master Scheduling

Material Requirements Plan Generation

MRP Planning Methods

Launching the Planning Process

Reviewing or Adding Plan Options


         Previous  Next          Contents  Index  Navigation  Glossary  Library