Previous | Next | Contents | Index | Navigation | Glossary | Library |
From the Horizontal Plan and Enterprise View windows, you can view not only the snapshot supply/demand information, but also the current status of supply/demand while implementing planned orders at any time. You can navigate to Horizontal Capacity Plan and view current data on resource requirements. It shows the current capacity requirements from existing discrete jobs, schedules, and unimplemented planned orders.
Note: Current data on resource requirements is not available in MPS plans.
Supply Chain Planning users can also compare snapshot and current data from the Enterprise View window.