Example

For example, assume you assign one asset to Capital Project Y at the project level. You charge the following expenditure items to the project, all of which are capitalizable and charged to the same CIP account:

Expenditure Type Expenditure Category Amount
Supplies Operating 5,000.00
Supplies Operating 20,000.00
Professional Labor 5,800.00
Clerical Labor 1,500.00
Computer Service Center 14,000.00
Meals Travel 300.00
Lodging Travel 500.00
Air Travel Travel 900.00
Miscellaneous Operating 5,000.00
TOTAL COSTS 53,000.00

If you group by Expenditure Category, Oracle Projects creates the following asset lines:

Labor 7,300.00
Operating 30,000.00
Service Center 14,000.00
Travel 1,700.00

If you group by Expenditure Type, Oracle Projects creates the following asset lines:

Air Travel 900.00
Clerical 1,500.00
Computer 14,000.00
Lodging 500.00
Meals 300.00
Miscellaneous 5,000.00
Professional 5,800.00
Supplies 25,000.00

If you group All, Oracle Projects creates the following asset line:

All 53,000.00

Prerequisites

   To generate summary asset lines for a single project:

   To generate summary asset lines for a range of projects:

See Also

Generate Asset Lines

Use Grouping Levels to Summarize Asset Costs

Adjusting Assets After Interface

Creating and Preparing Asset Lines for Oracle Assets

Reviewing Asset Lines


         Previous  Next          Contents  Index  Navigation  Glossary  Library