The following cost budget worksheet shows raw and burdened cost budgets.
Cost Budget | ||||||
Resource List: Labor by Employee and Job | ||||||
Budget Entry Method: Lowest Task, PA Period | ||||||
Notes: | Budget by resource | |||||
Task | Resource | Period | Qty. | UOM | Raw Cost | Burdened Cost |
1.1 | Marlin | P12-02-95 | 30 | Hours | 1,500 | 3,750 |
Travel | P12-02-95 | 1,000 | 1,200 | |||
Marlin | P12-03-95 | 30 | Hours | 1,500 | 3,750 | |
Travel | P12-03-95 | 1,000 | 1,200 | |||
Outside Services | P12-04-95 | 5,000 | 5,000 | |||
1.2.1 | Senior Consultant | P01-01-96 | 40 | Hours | 2,000 | 5,000 |
In-House Recoverables | P01-01-96 | 500 | 750 | |||
1.2.2 | Senior Consultant | P01-02-96 | 80 | Hours | 4,000 | 10,000 |
2 | Robinson | P01-03-96 | 50 | Hours | 5,000 | 12,500 |
In-House Recoverables | P01-03-96 | 1,000 | 1,000 | |||
Travel | P01-03-96 | 1,500 | 1,800 | |||
TOTAL: | 24,000 | 45,950 |