Midpoint Rescheduling
You can use midpoint rescheduling to reschedule around a bottleneck job operation. When you midpoint reschedule jobs, job start and completion dates and times are automatically updated. The start and completion dates of all other job operations, including operations you added that are not part of the original routing, are also updated. Material and resource requirement dates are also updated.
Prerequisites
To midpoint reschedule operations:
2. Select the discrete Job.
3. Choose the Find button to populate the Operations region with the job's operations.
You can choose any operation since any operation can be a bottleneck operation.
6. Choose either of the following options:
The reschedule date and time becomes the new FUSD or LUCD and time of the operation. Operations that are before the operation being rescheduled are backward scheduled from this date and time. Operations that are after it are forward scheduled. Job start and completion dates and times as well as resource and material requirement dates and times are also updated.
8. Choose OK to save your work.
To manually reschedule a job or schedule operation:
See Also
Rescheduling Discrete Jobs
Detailed Scheduling
Discrete Rescheduling