Project Team


It is a common practice to have a dynamic project team wherein the number and specialty of people varies according to the stage of the implementation. For example, Table 1 shows the breakdown of resources needed at each stage in NREC's implementation project.

Table 1. NREC's Project Resources
Project Stages
Project Manager
Lead Business Analyst
Lead Configuration Specialist
Lead Architect
Configuration Specialists
Architect
Training Specialist
Documentation Specialist
Definition
X
X
 
 
 
 
 
 
Discovery
X
X
X
 
 
 
 
 
Design
X
X
X
X
 
 
 
 
Configuration
X
X
X
X
X
 
 
 
Validation
X
X
X
X
X
X
X
X
Deployment
X
X
X
X
X
X
X
X