Changing Days of the Week for the Dispatch Board Gantt Chart (High-Interactivity Client)


By default the Gantt chart of the Dispatch Board displays Monday to Friday as the days when users can schedule activities. Saturday and Sunday are typically excluded. Some companies require that users schedule activities for employees on any day of the week, including Saturday and Sunday. In the following example task, you configure the Gantt chart of the Dispatch Board to display all 7 days of the week. For more information about performing configuration tasks with Siebel Tools, see Using Siebel Tools.

This task is a step in Process of Configuring the Dispatch Board (High-Interactivity Client).

To change the days of the week for the Dispatch Board Gantt chart

  1. Log in to Siebel Tools as an administrator.
  2. Lock the FS Dispatch Board project for editing.
  3. In the Object Explorer, navigate to Applet, and query for the FS DB Planned GanttChart AX Applet.
  4. Navigate to Applet, then Applet User Prop, and query for X-Display Constraint Map.

    The default value for this user property is #0#0#1#5#. This value indicates that 5 days of the week, Monday (indicated by the number 1) to Friday (indicated by the number 5), appear on the Gantt chart.

  5. Update the Value field as follows:

    #0#0#0#6#

    This value displays a 24-hour day, starting on Sunday (indicated by the last number 0) and ending on Saturday (indicated by the number 6).

  6. Compile the FS DB Planned GanttChart AX Applet, and replace the Siebel Repository File (SRF).
  7. Restart the client, and view the full week that appears on the Gantt chart of the Dispatch Board.
Siebel Field Service Guide Copyright © 2013, Oracle and/or its affiliates. All rights reserved. Legal Notices.