Running the Lot Start Process

This chapter provides an overview of the Lot Start process and discusses how to:

Click to jump to parent topicUnderstanding the Lot Start Process

To build and manage effectively, you must create a structure for establishing the budget, managing costs, creating commitments (purchase orders and subcontracts), managing suppliers and subcontractors, and revising lot configuration information. The Lot Start process helps you manage all of these tasks.

The Lot Start process is designed to:

The Lot Start process has three steps:

  1. Generate the workfile.

  2. Review and maintain the workfile.

  3. Generate commitments.

The Lot Start process produces several documents, including:

The JD Edwards EnterpriseOne Job Cost system and the JD Edwards EnterpriseOne Procurement system interface with the JD Edwards EnterpriseOne Homebuilder Management system to provide the structure for cost management, analysis, and control.

See Also

Interacting with the JD Edwards EnterpriseOne Job Cost System

Interacting with the JD Edwards EnterpriseOne Procurement System

Click to jump to parent topicWorking with the Lot Workbench

This section provides an overview of the Lot Workbench program (P44H200A), lists a prerequisite, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding the Lot Workbench Program (P44H200A)

Beginning with an initial review of all lots in a area, use the Lot Workbench program (P44H200A) to access a hierarchy of data, including groups of lots by status, a single lot, and a single option.

Use the P44H200A program to review and revise:

Note. You can review the job in the Job Status Inquiry program (P512000) by selecting Job Status from the Row menu on the Lot Workbench form.

Click to jump to top of pageClick to jump to parent topicPrerequisite

Before you complete the tasks in this section, you must set up any lot configuration information, including buyers and options.

See Processing the Sale of a House.

Click to jump to top of pageClick to jump to parent topicForm Used to Work with the Lot Workbench

Form Name

FormID

Navigation

Usage

Lot Workbench

W44H200AA

Build and Manage (G44H25), Lot Workbench

Review lot information.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Lot Workbench (P44H200A)

Processing options enable you to specify the default processing for programs and reports.

Default

Specify the default area to initially filter by

Specify a code from UDC 00/05 that identifies the default area. Large home builders might have many areas within their organizational structure. Smaller, regional builders might operate their entire organizations using a single area.

Specify the default community to filter on

Specify the default community.

Enter a '1' to group and display lots by status

Specify how to display lots within a community, phase, or both. Values are:

Blank: Display lots in lot sequence order.

1: Display lots by lot status code.

Versions

If you leave the following processing options blank, the system uses the ZJDE0001 version.

1. Community Master (P44H101) Version and 2. Phase Master (P44H101) Version

Specify the versions of the P44H101 program to use.

3. Job Master (P51006) Version

Specify the version of the P51006 program to use.

4. Pro Forma (P44H102) Version

Specify the version of the P44H102 program to use.

5. Sales Workbench (P44H500) Version

Specify the version of the P44H500 program to use.

6. Plan Master (P44H301) Version

Specify the version of the P44H301 program to use.

7. Option Master (P44H401) Version

Specify the version of the P44H401 program to use.

8. Lot Master (P44H201) Version

Specify the version of the P44H201 program to use.

9. Job Status Inquiry (P512000) Version

Specify the version of the P512000 program to use.

10. Option Selection (P44H501) Version

Specify the version of the P44H501 program to use.

11. House Revisions (P44H500) Version.

Specify the version of the P44H500 program to use.

12. Closing Worksheet (P44H591) Version

Specify the version of the P44H591 program to use.

13. Lot Start Workfile Maintenance (P44H711) Version

Specify the version of the P44H711 program to use.

Click to jump to top of pageClick to jump to parent topicReviewing Lot Information

Access the Lot Workbench form.

To review lots:

  1. Enter values in the Area and Community fields.

  2. To review lot information by status, click the Display Lots by Status check box and click Findor Refresh.

  3. Expand any of the statuses listed below to review the lots associated with that status:

  4. To review all of the lots in the community, clear the Display Lots by Status check box and click Find or Refresh.

  5. Expand the community to see all the lots.

    Regardless if whether you select or clear the Display Lots by Status check box, the system displays the following buttons next to each lot to indicate its status:

    Button

    Status

    Gray or White House

    House in Process/Details Available

    Green House

    House in Closed

    Blue House

    House is a Model

  6. To review information about a lot, select a lot and then select the Lot/Construction and Sales Details tabs.

  7. To review the options that are attached to the lot, expand the lot.

    The system displays one of the following buttons to indicate the option status:

    Button

    Option Status

    Red filing cabinet

    No commitments have been generated for the option.

    Gray filing cabinet

    Commitments have been generated for the option.

  8. To review information about a specific option, select the option and review the information available on the Option Details tab.

  9. To review additional information, select a community, phase, or lot, and then select one of the programs, such as Community Master or Option Master, from the Row menu.

Click to jump to parent topicGenerating the Lot Start Workfile

This section provides overviews of the Lot Start Workfile Generation program (R44H700) and the data selection hierarchy, lists prerequisites, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding the Lot Start Workfile Generation Program (R44H700)

To begin the Lot Start process, you must first run the Lot Start Workfile Generation program (R44H700) to generate records in the Lot Start Workfile (F44H711). The workfile records contain detail by lot, cost code, and contract number and specify whether the price was determined by national purchasing. You can use the Work with Lot Start Workfile form to manage budgets and commitment generation.

You can run the R44H700 program in one of these three modes:

When you generate the F44H711 workfile, the system integrates the following information from other tables in the JD Edwards EnterpriseOne Homebuilder Management system:

Information

Table

Bid information

Bid Header (F44H601)

Bid Details (F44H611)

Takeoff information

Takeoff Master (F44H602)

Item pricing information

Material Item Pricing (F44H603)

Options

Option Selections (F44H511)

Commitment start date

Lot Master (F44H201)

Supplier assignment

Vendor Assignment (F44H604)

During the initial workfile generation, the system uses this information:

You must specify a commitment start date in the processing options before you run the Lot Start Workfile Generation program. You can either enter a date or specify that the system uses the date that appears in the Lot Master table (F44H201).

When you run the R44H700 program, the system assigns a lot start generation number to each record that is created. You can use this number to search for a workfile record in the Lot Start Generation Workfile (F44H71W1). The system will enter a flag next to each bid and takeoff record that uses the national purchasing item prices. Each record also has a lot construction sequence number in the Lot Master (F44H201). You can either manually preassign that number or let the system automatically assign the next available sequence number. The system maintains lot construction sequence numbers within each community only.

You can review tax information for bid contracts and takeoffs, when available, on the Workfile Detail Preview form. For example, you can view the tax commitment amount for taxable lines. If the takeoff detail records do not contain tax information, the system first searches the job, and then the supplier address book for tax information.

Click to jump to top of pageClick to jump to parent topicUnderstanding the Data Selection Hierarchy

The Lot Start Workfile Generation program (R44H7000) analyzes bids and takeoffs and, using supplier assignments, determines the appropriate commitments and budgets to create for each lot. When multiple bids and takeoffs exist for a specific cost code, the system uses a set of defined rules and hierarchies to determine which items to select.

The R44H700 program uses a specific to general selection hierarchy for supplier assignments and bids, and cumulative selection for takeoffs. For bids, the program selects transactions in this hierarchical order:

  1. Any detail transactions for bids that are designated as preferred subcontractor.

    You can designate a supplier as a preferred subcontractor. If a preferred subcontractor exists for a cost code, or a cost code and option combination, the R44H700 program selects that bid and the search is finished. The R44H700 program selects a preferred subcontractor at any tier level even when there is a more specific, nonpreferred supplier bid at a more detailed level. If a preferred subcontractor is used, national purchasing is bypassed.

  2. Supplier assignments.

    A bid requires a supplier assignment when no preferred subcontractor is designated.

  3. Bid detail transactions for all assigned suppliers.

When multiple valid bid records appear at the same level of specificity, the R44H700 program selects all of them.

Note. You must understand the hierarchical order in which the R44H700 program chooses supplier assignment, bid, and takeoff records to use wildcards efficiently and ensure predictable and accurate results.

Supplier Assignment Hierarchy

You define a supplier assignment at the area level, but you can also further define the assignment at the community, phase, lot, or option level. You can also define a supplier within the national purchasing structure.

The R44H700 program first searches for the greatest level of specificity. If it finds no matching record, the system continues to the next level, and so on. The eight levels of specificity for supplier assignments, from most specific to most general, are:

Level

Community

Phase

Lot

Option

1

Community

Phase

Lot

Option

2

Community

Phase

Lot

A wildcard value

3

Community

Phase

A wildcard value

Option

4

Community

Phase

A wildcard value

A wildcard value

5

Community

A wildcard value

A wildcard value

Option

6

Community

A wildcard value

A wildcard value

A wildcard value

7

A wildcard value

A wildcard value

A wildcard value

Option

8

A wildcard value

A wildcard value

A wildcard value

A wildcard value

If the R44H700 program does not find a preferred subcontractor, it searches for an assigned supplier in the order illustrated in the previous table. The program selects the most specific assignments for a bid for the appropriate date range. For example, the commitment start date is within the start and expiration dates of the supplier assignment record. When the system finds all valid supplier assignment records (all assignments at the same level are valid), it uses the associated bid or takeoff record.

Bid Hierarchy

The R44H700 program first searches for the greatest level of specificity. If the system does not find a matching record, the system continues to the next level, and so on. The nine levels of specificity for bid detail records, from most specific to most general, are:

Level

Community/Area

Phase

Plan

Elevation

1

Community

Phase

Plan

Elevation

2

Community

Phase

Plan

A wildcard value

3

Community

Phase

A wildcard value

A wildcard value

4

Community

A wildcard value

Plan

Elevation

5

Community

A wildcard value

Plan

A wildcard value

6

Community

A wildcard value

A wildcard value

A wildcard value

7

Area

A wildcard value

Plan

Elevation

8

Area

A wildcard value

Plan

A wildcard value

9

Area

A wildcard value

A wildcard value

A wildcard value

The R44H700 program selects the contract lines that are at the most specific level for every cost code and for every cost code and option combination that you are processing. When two contracts are set up at the same level for the same cost code, or the same cost code and option combination, the system selects both contracts. If the system selects a supplier assignment record with a National Purchasing Area, the system will use the associated national purchasing information.

Takeoff Hierarchy

The R44H700 program searches all levels of the organizational structure of the takeoff, such as area, community, and phase, to find all material requirements. Takeoff selection is cumulative. For example, the system creates a purchase order for 3655 bricks during the Lot Start process if the following information applies:

If the system selects a supplier assignment record with a national purchasing area, the system will use the associated national purchasing information, such as the national commodity item number and material pricing information.

Click to jump to top of pageClick to jump to parent topicPrerequisites

Before you complete the tasks in this section, you must:

Click to jump to top of pageClick to jump to parent topicRunning the Lot Start Workfile Generation Program

Select Building and Manage (G44H25), Lot Start Workfile Generation.

Click to jump to top of pageClick to jump to parent topicSetting Data Sequencing for the Lot Start Workfile Generation Program

Do not change the existing data sequencing because unpredictable results might occur.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Lot Start Workfile Generation (R44H700)

Processing options enable you to specify the default processing for programs and reports.

Process

1. Processing Mode

Specify the mode in which to run the program. Values are:

Blank: Prestart.

1: Proof.

2: Final.

Note. Prestart mode does not create workfile records or process according to the processing options. Prestart mode copies accounts from the area job to the new lot job for the cost code range specified in the Cost Code From (Prestart Only) and Cost Code Through (Prestart Only)processing options.

2. Cost Code From (Prestart Only) and 3. Cost Code Through (Prestart Only)

Specify the cost code range for which the system copies amounts from the area job to the new lot job when the program is in prestart mode and the value in the Copy Budgets From Cost Code Template processing option is 1.

4. Post Next Posting Stage

Specify the posting stage through which to process transactions. The posting stage corresponds to reporting code 3 (R003) in the Account Master table (F0901). Values are:

Blank: Post through the ending posting stage that you specify in the Through Posting Stage processing option.

1: Post through the next posting stage.

This value is the next higher value listed in the F0901 table for the cost code template. When you generate the lot start workfile, alphabetic values are not supported in reporting code 3.

5. Through Posting Stage

Specify the posting stage through which commitments, budgets, or both are created. The posting stage corresponds to reporting code 3 (R003) in the F0901 table.

Note. The system ignores the value for this processing option if the value in the Post Next Posting Stage processing option is 1.

6. Copy Budgets from Cost Code Template

Specify whether to copy budgets from the cost code template on the Plan Master Revisions form to the new lot. Values are:

Blank: Do not copy.

1: Copy.

7. Create Budgets

Specify whether or how to create budgets when you run the program. Values are:

Blank: Do not create budgets.

1: Create budgets through the posting stage for which the record is run. Budgets are created for the Base House and Options fields. Additionally, Base House creates budgets from Budget Only Bids for each account that does not result in a workfile record.

2: Create budget for the entire lot or job.

The budgets for cost codes after the current posting stage are calculated from bids and takeoffs in the JD Edwards EnterpriseOne Procurement system.

3: Create budgets using budget-only bids for cost codes after the posting stage.

8. Budget Creation Process

Specify when budgets are created for records in the F44H711 workfile. Use this processing option in conjunction with the Create Budgets processing option. Values are:

Blank: Create budgets when you run the Lot Start Workfile Generation program (R44H700).

1: Create budgets when you run the Generate Homebuilder Commitments program (R44H7113).

Note. Regardless of how you set this processing option, all budget amounts that are not written to the F44H711 workfile, such as budget-only records and budget records that are not within the posting stage, are created when you run the R44H700 program.

9. Costing Method

Specify how to cost the budget and commitments when the program is run in proof or final mode. Budgets and commitments can have cost components resulting from bids, takeoffs, or both. Values are:

Blank: Process bids and takeoffs

1: Process bids

2: Process takeoffs

10. Commitment Effective Date

Specify the commitment effective date for bid and takeoff processing. If you leave this processing option blank, the system uses the Commitment Start Date (COMJ) in the F44H201 table.

11. Takeoff Discounts

Specify the type of discount to be taken on takeoff-related commitments. Values are:

1: Model discount. For the system to calculate a model discount, the lot must be marked as a model and the model pricing fields must be set on the item price record.

2: Standard discount. For the system to calculate a standard discount, the item price record must be set up.

3: No discounts (default).

12. Retention Calculation

Specify how retention information for material items is calculated. Values are:

Blank: Do not apply retention to material items.

1: Apply retention to all material items.

2: Apply retention to base house material items.

Note. If you specify 1 or 2 for this processing option, you must enter a value in the Retainage % (retention percentage) field on the Item Price Revisions form. The bid header retention is stored in the F44H711 workfile.

13. Advance To Construction Activity Rule

Specify the next construction activity rule from UDC 44H0/RL the system sets in the F44H201 table after you run the program.

14. Commitment Generation

Specify whether to run the Generate Homebuilder Commitments program (R44H7113) when you run the R44H700 program in final mode. Values are:

Blank: Do not run.

1: Run.

Account Creation

1. Lot Job - Business Unit Type

Specify the job type from UDC 00/MC to use in the Business Unit Master table (F0006). If you leave this processing option, the system uses the lot job type from the constants.

2. Lot Job Description Flag

Specify which description appears when you run the Lot Start Workfile Generation program. Values are:

Blank: The default description from the Lot Job - Default Description processing option.

1: The Community Description field (DL01) from the F44H101 table.

2: The Comment field (LOTCMT) from the F44H201 table.

3: The Lot Address field (LOTADD) from the F44H201 table.

3. Lot Job Default Description

Specify the name for the lot job.

If you leave the Lot Job Description Flagprocessing option blank, this default description appears in the Lot Job Master Description field.

4. Lot Job Category Code 6 through 7. Lot Job Category Code 9

Specify user-defined codes from UDC 00/06 through UDC 00/09 in the Business Unit Master table (F0006).

8. Lot Job Category Code 10

Specify the value to update in the Category Code 10 field in the F0006 table. Values are:

Blank: Update this field with the value specified in the Category Code 10 Default Value processing option.

1: Update this field with the phase number from the F44H201 table.

9. Category Code 10 Default Value

Specify a code from UDC 00/10 that is the default value n the F0006 table.

Versions

1. Commitment Generation (R44H7113) Version

Specify the version of the R44H7113 program to use for each processed lot. If you leave this following processing options blank, the system uses the XJDE0001 version.

2. Lot Master Outbound Notification (P44H9903) Version

Specify the version of the scheduling P44H9903 program to use when scheduling is enabled and the lot master has not already been processed. If you leave this following processing options blank, the system uses the ZJDE0001 version.

3. Commitment Outbound Notification (P44H9904) Version

Specify the version of the scheduling P44H9904 program to use when scheduling is enabled and TBD bids are created. If you leave this following processing options blank, the system uses the ZJDE0001 version.

Click to jump to parent topicManaging Information in the Lot Start Workfile

This section provides overviews of lot start workfile management, canceling and deleting records in the F44H711 workfile, and supplier TBD assignment, lists a prerequisite, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Lot Start Workfile Management

After you run the Lot Start Workfile Generation program (P44H711), you can manage the information at a detailed level in the Lot Start Workfile (F44H711) using established activity rules.

Use the Lot Start Workfile Review (P44H711) to manage information in the F44H711 workfile. Managing information includes:

Unless you delete records, the lot start information remains in the F44H711 workfile after the system processes the lot in the JD Edwards EnterpriseOne Job Cost and JD Edwards EnterpriseOne Procurement systems. This information provides an important audit trail between the purchasing detail information and the information in the JD Edwards EnterpriseOne Procurement system.

Record Status in the Lot Start Workfile

This table shows the correlation between the color of a record in the detail area of the Work with Lot Start Workfile form and the commitment status of the record:

Record Color

Commitment Post Status

Commitment Post Status Description

Black

Blank

Ready for commitment generation.

Gray

C

Canceled. The system does not create commitments again when at this status.

Green

E

Estimated takeoff awaiting final quantity.

Blue

T

TBD supplier. The system needs a supplier to create the commitment.

Purple

H

On hold. The system cannot create the commitment.

Red

P

Commitment generated.

Red or Silver

P

Commitment is partially paid or relieved.

See Understanding Commitment Processing.

Workfile records with a commitment status of P include additional detail to alert you of additional transactions that occur in the JD Edwards EnterpriseOne Procurement system.

For records with a commitment status of P, this table shows the correlation between the color of a record in the detail area of the Work with Lot Start Workfile form and the transaction status:

Record Color

Transaction Status

Description

White

No button

A commitment was generated in JD Edwards EnterpriseOne Procurement, but has not been relieved. For example, goods or services have been received, but a payable voucher has not been created for the commitment.

White

Red X

A commitment has been generated, but no associated commitment record can be found.

Gray

No button

A commitment has been partially relieved in the JD Edwards EnterpriseOne Accounts Payable system, but an open balance on the commitment still exists.

Gray

Green check

A commitment has been fully relieved.

Records with a 1 in the Natl Pur field on the Work with Lot Start Workfile form use national purchasing prices.

Click to jump to top of pageClick to jump to parent topicUnderstanding Canceling and Deleting Records in the F44H711 Workfile

You should be cautious when canceling or deleting workfile records because it might affect budgets or commitments. This table describes what the system does when you cancel and delete records in the F44H711 workfile, based on the budget and commitment statuses:

Budget Post Status

Commitment Post Status

User Action

System Action

0 or 1

P

Delete or Cancel

Performs one or more of these functions:

  • Reverses the budget for the amount of the record.

  • Cancels the unrelieved commitment.

  • If the posted record originated from a supplier TBD transaction, deletes both the posted record and the original TBD.

  • Changes the commitment posting status to C.

0

T

Delete or Cancel

If a supplier is assigned to the TBD transaction and the child transaction has already been deleted, deletes the record in the F44H711 workfile.

If no supplier is assigned to the TBD transaction, deletes the record in the F44H711 workfile.

0

Blank

Delete

If the transaction is a supplier TBD transaction, deletes both the parent TBD and the child supplier-assigned records in the F44H711 table.

If the transaction is not a supplier TBD transaction, deletes only the selected record in the F44H711 workfile.

0

Blank

Cancel

Changes the commitment posting status to C.

0

E

Delete

Deletes the record in the F44H711 workfile.

0

E

Cancel

Changes the commitment posting status to C.

0

H

Delete

Deletes the record in the F44H711 workfile.

0

H

Cancel

Changes the commitment posting status to C.

1

T

Delete or Cancel

If a supplier is assigned to the TBD transaction and the child transaction has already been deleted, deletes the record in the F44H711 workfile.

If no supplier is assigned to the TBD transaction, the system does one of the following:

  • Reverses the budget for the amount of the record and deletes the record in the F44H711 workfile.

  • Changes the commitment posting status to C.

1

Blank

Delete

If the transaction is a supplier TBD transaction:

  • Reverses the budget for the amount of the record.

  • Deletes both the parent TBD and the child supplier-assigned transactions.

If the transaction is not a TBD supplier-assigned transaction:

  • Reverses the budget for the amount of the transaction.

  • Deletes only the selected record in the F44H711 workfile.

1

Blank

Cancel

Reverses the budget for the amount of the record.

Changes the commitment posting status to C.

1

E

Delete or Cancel

Reverses the budget for the amount of the record.

Deletes the selected record in the F44H711 workfile.

Changes the commitment posting status to C.

1

H

Delete or Cancel

Reverses the budget for the amount of the record.

Deletes the selected record in the F44H711 workfile.

Changes the commitment posting status to C.

Click to jump to top of pageClick to jump to parent topicUnderstanding Supplier TBD Assignment

Often, you are unable to determine which supplier will be performing certain tasks until the time of construction. The supplier to be determined (TBD) feature streamlines the process of updating a bid or a takeoff with the correct supplier number. If you do not use the supplier TBD feature, you must cancel the existing purchasing document and create a new commitment with the appropriate supplier.

When you assign suppliers to specific commitments, the system stores the information in the Lot Start Workfile (F44H711). The system updates the records in the F44H711 workfile with the supplier number and supplier description, as defined on the Supplier Assignment Maintenance form.

Where appropriate, the supplier TBD feature allows you to update pricing based on the newly-assigned supplier's prices. You can modify uncommitted transactions on the Select from Allowed Suppliers form , and process the transactions in the Generate Homebuilder Commitments program (R44H7113).

Click to jump to top of pageClick to jump to parent topicPrerequisite

Before you complete the tasks in this section, you must verify that the supplier assignment is set up.

See Assigning Suppliers to Areas.

Click to jump to top of pageClick to jump to parent topicForms Used to Manage Information in the Lot Start Workfile

Form Name

FormID

Navigation

Usage

Work with Lot Start Workfile

W44H711A

After Start Commitments and Costing (G44H24), Lot Start Workfile Review

  • Review lot records.

  • Cancel workfile records.

  • Delete workfile records.

  • Place workfile records on hold.

  • Release workfile records on hold.

  • Revise takeoff quantities.

Workfile Detail Preview

W44H711B

On the Work with Lot Start Workfile form, select a record and click Select.

Review detailed lot information.

After Start Processing

W44H706A

On the Work with Lot Start Workfile form, select a record and select Revise Takeoff from the Row menu.

Revise takeoff quantities in the F44H711 workfile.

Select from Allowed Suppliers

W44H704A

On the Work with Lot Start Workfile form, select a supplier TBD record and select Assign Supplier from the Row menu.

Assign suppliers to TBD records.

Note. A supplier TBD record is indicated by blue text and the value T in the Commitment Post Status field.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Lot Start Workfile Review (P44H711)

Processing options enable you to specify the default processing for programs and reports.

Defaults

Homebuilder Area ID

Specify a code from UDC 00/05 that determines the default area to use on the Work with Lot Start Workfile form.

Community

Specify the community to use on the Work with Lot Start Workfile form.

Phase Number

Specify the default phase to use as a filter on the Work with Lot Start Workfile form.

Versions

1. Commitment Generation (R44H7113) Version

Specify the version of the R44H7113 report to use. If you leave this processing options blank, the system uses the XJDE0001 version.

2. Purchase Order Entry (P4310) Version

Specify the version of the P4310 program to use. If you leave this processing options blank, the system uses the ZJDE0001 version.

3. Commitment Outbound Notification (P44H9904) Version

Specify the version of the P44H9904 program to use when scheduling is enabled. If you leave this processing options blank, the system uses the ZJDE0001 version.

Budgets

Enter '1' to create F0911 audit trail records when doing budget reversals

Specify whether to create audit trail records in the Account Ledger table (F0911) when you cancel or delete workfile records that have posted budgets. Values are:

Blank: Do not create audit trail records.

1: Create audit trail records.

Enter the budget amount ledger type to use for budget reversals

Specify the amount ledger type to use when reversing original budgets in the JD Edwards EnterpriseOne Job Cost system when you cancel or delete workfile records. If you leave this processing option blank, the system uses ledger type JA.

Note. This ledger type must match the amount ledger type specified in the processing options for the Generate Homebuilder Commitments program (R44H7113).

Click to jump to top of pageClick to jump to parent topicCanceling Workfile Records

Access the Work with Lot Start Workfile form.

To cancel a workfile record, select a record and then select Cancel from the Row menu.

When you select a single record or an entire lot to cancel, the system:

Click to jump to top of pageClick to jump to parent topicDeleting Workfile Records

Access the Work with Lot Start Workfile form.

You can delete records as often as necessary. Deleted records appear as deleted the next time you run the R44H700 program.

Select a record and click Delete.

Click to jump to top of pageClick to jump to parent topicPlacing Workfile Records on Hold

Access the Work with Lot Start Workfile form.

Select a record and then select Hold from the Row menu.

You can place a hold on records in the F44H711 workfile to prevent the system from generating commitments for those transactions. The system changes the Com PS (commitment posting status) field to H and the text color to purple to indicate the transaction is on hold.

Note. You can only place records with a blank commitment posting status on hold.

Click to jump to top of pageClick to jump to parent topicReleasing Workfile Records on Hold

Access the Work with Lot Start Workfile form.

Select a record and then select Release from the Row menu.

You can release the records on hold when you are ready to continue processing them.

Note. After you release a record that was on hold, the system returns the commitment posting status to blank.

Click to jump to top of pageClick to jump to parent topicRevising Takeoff Quantities

Access the Work with Lot Start Workfile form.

To revise takeoff quantities:

  1. Enter values in these fields on the Work with Lot Start Workfile form:

  2. Select a record and then select Revise Takeoff from the Row menu.

    You can revise only records that have a value of Ein the Com PS(commitment posting status) field.

  3. On the After Start Processing form, enter a value in the Quantity field and click OK.

Click to jump to top of pageClick to jump to parent topicAssigning Suppliers to TBD Records

Access the Select from Allowed Suppliers form.

To assign TBD suppliers:

  1. Select a blue record on the Work with Lot Start Workfile form and select Assign Supplier from the Row menu.

  2. Click Find on the Select from Allowed Suppliers form to view available suppliers for the header information.

  3. Select a supplier and click Select to assign a supplier to the TBD record.

  4. On the Work with Lot Start Workfile form, the system will recalculate the price for both bids and takeoffs after the supplier is selected.

Click to jump to parent topicGenerating Homebuilder Commitments

This section provides an overview of budget and commitment generation, lists a prerequisite, and discusses how to:

Click to jump to top of pageClick to jump to parent topicUnderstanding Budget and Commitment Generation

There are three ways in which you can create budgets and commitments:

If you create commitments manually on the Work with Lot Start Workfile form, select only one record to generate commitments for all eligible records for a lot. The system generates commitments for those records with a blank commitment posting status. The system processes the selected lot and then updates the Com PS field on the Work with Lot Start Workfile form with the value P.

When commitments are generated in the JD Edwards EnterpriseOne Homebuilder Management system, records are also created in the JD Edwards EnterpriseOne Procurement system, specifically in the Purchase Order Header (F4301) and Purchase Order Detail File (F4311) tables. The system also updates the Procurement fields, such as Original Document, Document Type, Original Line Number, and so on, with the corresponding information from the bids or takeoffs.

Click to jump to top of pageClick to jump to parent topicPrerequisite

Before you complete the task in this section, you must verify that the takeoff document type exists in UDC 40/CT to ensure that the system creates proper PA ledger commitments.

Click to jump to top of pageClick to jump to parent topicRun the Generate Homebuilder Commitments Program

Select Build and Manage (G44H25), Generate Homebuilder Commitments.

When you specify the data selection, the system prompts you to generate workfile records for a specific area, community, phase, or lot only.

Do not change the existing data sequence because unpredictable results might occur.

Click to jump to top of pageClick to jump to parent topicSetting Processing Options for Generate Homebuilder Commitments (R44H7113)

Processing options enable you to specify the default processing for programs and reports.

Defaults

1. Commitment Generation Mode

Specify the mode in which to run the program. Values are:

Blank or 0: Proof mode generates a report of the budgets and commitments created, but does not update records.

1: Final mode updates the records that you specify in the processing options.

2. Contract Type

Specify the types of contracts that the system searches for. Values are:

Blank or 0: Process bid contracts and takeoffs (default).

1: Process bid contracts only.

2: Process takeoffs only.

3. Takeoff Detail Level

Specify how to group commitments when you run the R44H7113 program. Values are:

Blank: Group commitments by cost code into multiple contracts for a single supplier with separate cost codes.

1: Group commitments by supplier number into one contract containing multiple accounts and multiple items.

4. Save Temporary Workfiles (F44H73W1, F44H73W2)

Specify whether to save workfile records after you run the R44H7113 program.

This program creates two temporary workfiles, the Lot Start - P.O./Commitment Generation Workfile (F44H73W1) and the Lot Start - Budget Generation Workfile (F44H73W2), to store commitments and budgets for both posting and printing. When a contract does not post successfully, you can review the records for troubleshooting purposes. Values are:

Blank: Do not save workfile records (default).

1: Save workfile records. This can require a large amount of disk space.

Versions

If you leave either of the following processing options blank, the system uses the ZJDE0001 version.

1. Purchase Order Entry (P4310) Version

Specify the version of the P4310 program to use.

2. Commitment Outbound Notification (P44H9904) Version

Specify the version of the P44H9904 program to use when scheduling is enabled.

Budgets

1. Budget Ledger Type for Commitment Generation

Specify a code from UDC /LT that identifies the amount ledger type to use to create original budgets in the JD Edwards EnterpriseOne Job Cost system when you run the Generate Homebuilder Commitments program. If you leave this processing option blank, the system uses the default ledger type, JA.(job cost budget amount).

The budgets might come from original budgets that are attached to the template job, commitment budgets in the bid master, or actual commitment records.

Note. The ledger type that you specify in this processing option must match the amount ledger type specified in a processing option for the Lot Start Workfile Maintenance program (P44H711).